Question:
Let's say you want to employ the Kaizen cultural practice in your company. What are the four main factors in the Kaizen cycle?

  1. plan, design, review, and launch
  2. plan, do, check, and act
  3. plan, don’t do, lie, and act
  4. plan, analyze, design, and implement
Answer:
B - is the correct answer